Highland Schools in Ohio First to Connect to Medina County Fiber Network

Quite some time ago, we let you know about the plans and funding for the Medina County Fiber Network (MFCN). The network, owned by the Medina County Port Authority (MCPA) began construction in March, 2011, and is nearing completion. Jennifer Pignolet, reported in the Medina GazetteOnline, that the network just signed on their first customer, Highland Schools.

Apparently, the schools contract with its current provider, Time Warner Cable, is about to expire. While connecting Highland Schools now may be ahead of schedule, the county fiber committee can accommodate their needs. As an added bonus, the new relationship is more economical for the schools. From the article:

“Their situation needing to be addressed immediately certainly moved them to the front of the line,” [said Jim Gerspacher, chairman of the county’s fiber committee].

While the $14 million network is still months away from full completion, Gerspacher said there is enough infrastructure in place to get Highland online.

The school will have full Internet and phone service and will have all its buildings connected to one network.

Highland Technology Director Roger Saffle said the district will save close to $90,000 a year by switching from Time Warner to the Medina County network.

“It will maintain the access we already have with a cheaper cost,” Saffle said.

Highland Schools is moving from a $100,000 per year Time Warner Cable contract (or about $8,333 per month). The schools now will pay $1,500 each month to the MCPA and, according to Saffle, will be able to apply for federal grant funding to recover 40% of that monthly fee.

In 2008, OneCommunity and the MCPA began a partnership to plan and build the network. OneCommunity received a $44 million broadband stimulus grant in 2010 to extend fiber to 22 Ohio counties. MCPA received $1.6 million of that stimulus for their County network. The remainder of the $13.8 million project was covered by 20-year revenue development bonds issued by the MCPA.

OneCommunity will manage operations when the project is complete.