In 2014, West Virginia wrote its Broadband Plan, but since then much has changed in the state, in the country, and with technology. Officials from the West Virginia Broadband Enhancement Council have now released a Request for Information on Actions and Partnerships to Advance Last Mile and Middle Mile Broadband Services in West Virginia (RFI). Responses are due November 4th and early responses are encouraged.
Multi-Purpose RFI
According to the RFI, the state has several reasons for releasing the RFI:
The Council hopes to receive responses from:
Some of the goals that the program hope to fulfill include defining target areas that are unserved and helping local cities and counties in West Virginia obtain gigabit connectivity. The state is working with the National Telecommunications and Information Administration (NTIA) on the latter’s mapping initiative. The project is intended to better map Internet access and improve accuracy on a more granular level.
For details on the program goals related to middle mile and last mile projects, review the full RFI here. The Council wants input from outside entities on a number of factors as they update their Broadband Plan and work to expand broadband coverage in the state.
Important Dates
The RFI states that the Council will accept responses on a rolling basis until November 4th 2019, but they encourage early responses.
The RFI also states:
Internet Service Providers who may be interested in working with electric utilities on feasibility studies into middle-mile infrastructure to be completed in 2019 are strongly encouraged to respond with a preliminary expression of interest by October 14, 2019. ISPs who submit a preliminary expression of interest will be contacted to discuss additional information that the Council and the ISP may need to help identify if areas under study by electric utilities are suitable for last-mile projects of interest to the ISP.
This morning, the Department of Treasury announced the first round of Capital Projects Fund (CPF) awards to states putting together portfolios to deploy new infrastructure to unserved households.
Tens of billions of dollars in federal funding are poised for new broadband infrastructure deployment over the next five years. But a crucial step in allocating funds from the Broadband Equity, Access, and Deployment (BEAD) Program lies in knowing where fast, affordable, reliable broadband access currently is, so that they know where to drive new investment. A new federal broadband map is currently under construction, but many states aren't waiting around and have begun to develop their own broadband maps. In classifying the various state-led efforts, we've developed a new resource we're releasing today to serve as an easy reference guide. It shows how states are going about mapping Internet access, and which ones we think are doing it better than others. We’re calling it our United State(s) of Broadband Maps.