Chugging Along the FTTH Train in Chanute

In Chanute, the “Hub of Southeast Kansas” named in honor of railroad engineer and aviation pioneer Octave Chanute, the track this small city of approximately 9,100 is on to build its Fiber-to-the-Home (FTTH) network is a long one.

It began back in 1984 when the city’s utility department installed four miles of fiber optic cable to monitor and control its electric grid. The project was almost derailed in 2015 when three new Chanute City Commissioners voted to halt a $16.4 million bond issuance moments after they were sworn into office. City officials also had to contend with AT&T, which offered DSL service in the region. Aiming to stave off competition, the telecom giant petitioned the Kansas Corporation Commission to enforce a 1947 state law that requires permission from the state to issue bonds for utility projects.

Today, however, thanks to $1.6 million from the state – part of a $50 million statewide Connectivity Emergency Response Grant established in October 2020 by Kansas Gov. Laura Kelly in response to the COVID 19 crisis – Chanute is chugging toward a citywide build-out neighborhood-by-neighborhood.

Nearly Complete

Construction to further expand the network began at the Google mural at the intersection of Lincoln and Main, which commemorates the city’s distinction of being the center of the earth on Google Maps for Apple computers thanks to the fact that the software developer, Dan Webb, was from Chanute.

The current take-rate for the area from Main Street to 7th and Santa Fe to as far over as Katy Ave is 30%, IT Director Chris Stogsdill told us this week. “We are at about 33% for our take rate in the area from 3rd Street to 14th Street and right at about 53% in the Hillside/Sunset Subdivisions,” he added, noting that residential customers are getting 1 Gigabit per second (Gbps) speed with no data caps for $75 a month.

Kansas Sees Boost with Establishment of Broadband Office and Tens of Millions in Grants

Tens of thousands of homes, businesses, farms, schools, and community anchor institutions in the Sunflower State will see better connectivity options over the next few years. A recent executive order [pdf] establishing a Kansas Office of Broadband Development followed by the announcement of more than $49 million in grants to 67 projects around the state means a host of Fiber-to-the-Home (FTTH), fixed wireless, and institutional networks will break ground in the near future. The measure comes in response to the ongoing Covid-19 pandemic.

A Broadband Office and Grant Program

The new Office of Broadband Development has been placed in the state’s Department of Commerce, and given the task of promoting networks of all kinds — municipal, cooperative, private, and nonprofit — as well as supporting regional initiatives, developing a better broadband map, and removing policy barriers to fast deployment. 

The state actually has two grant programs ongoing at the moment as part of the connectivity program approved the state’s Strengthening People and Revitalizing Kansas (SPARK) Taskforce and the State Finance Council. The Broadband Partnership Adoption Grants (BPAG) are designed to help low-income Kansans pay for service with existing plans. The large pot of grant money just announced, on the other hand, is part of the Define Connectivity Emergency Response Grant (CERG), which will use CARES funding to facilitate new builds between now and the end of the year.

We Mourn the Loss of Two Broadband Champions

We are saddened to learn that two quiet champions of broadband have passed away — one recently and one about a year ago, although we only recently learned of his passing. Drew Davis of Larimer County, Colorado, and Larry Gates from Chanute, Kansas, performed the heavy lifting behind the scenes to help move their communities forward with essential investments. Both men and their quiet determination will be missed in their communities and by us.

Drew Davis and Discovering Larimer County

We spoke with Drew last summer when he came on the Community Broadband Bits podcast for episode 311. As Program Manager for Larimer Broadband, he and Director of Economic and Workforce Development Jacob Castillo and CIO Mark Pfaffinger joined discussed results of the county’s feasibility study survey. Drew was instrumental in developing the county plan as they find a way to bring better connectivity to people in Larimer County.

Drew was always helpful whenever we needed information about what was happening in the Colorado broadband world. He was a leader and strived to help others, including in the Larimer County Sheriff’s Department and Search and Rescue.

We know that folks in Colorado are also grieving his potential as well as the loss of his presence. Colin Garfield, who was one of the leaders of the municipal broadband effort in Fort Collins writes:

"Drew was a trusted adviser, a formidable ally to our efforts, and a local visionary who will be dearly missed. His contributions and leadership for rural broadband and policy flashed local brilliance. As northern Colorado becomes a stronghold for local connectivity, Drew's contributions, vision, and compelling arguments will not be forgotten. I'm grateful for the many enlightening, humorous, and blunt conversations we had over the past three years - I'm lucky to have even had the opportunity to cross paths with him."

Larry Laid the Foundation

Chanute, Kansas, to Deploy FTTH in Two Residential Neighborhoods

About four years ago, city commissioners in the community of Chanute, Kansas, stepped back from plans to finance a Fiber-to-the-Home (FTTH) project. At the time, newly elected city leaders decided not to pursue the project, but Chanute once again has fiber on their list of priorities. Late in June, the current city commission voted 3 - 1 to deploy FTTH in two neighborhoods

Requested by Residents

Residents from the Hillside/Sunset subdivisions and the neighborhood between 7th and 14th streets approached the city and asked to be connected. The pilot areas will include approximately 344 premises; city staff estimate connecting them will cost approximately $550,000. The vote in June authorized the city to spend idle funds from the electric utility with an expected payback within three year years.

Subscribers will pay $75 per month for gigabit connectivity, authorized by vote at the same meeting. The city will offer month-to-month service and will charge $135 to reconnect if a subscriber cancels but wants to sign up again later.

AT&T offers DSL in most of the city and CableOne has offered cable Internet access in Chanute for years, but residents are increasingly looking for the speed and reliability of fiber connectivity.

Fiber in Chanute

We wrote about Chanute’s investment in fiber connectivity and complementary fixed wireless for local businesses, schools, and municipal facilities back in 2013 in our report, "Chanute's Gig: One Rural Kansas Community's Tradition of Innovation Led to a Gigabit and Ubiquitous Wireless Coverage." The community was able to develop their gigabit network, which began with as a way to improve utility operations, with no bonding or borrowing.

Community Fiber Network Diversifying Economy in Louisiana

Acadiana, the southern region of Louisiana, is seeing a resurgence of industry thanks in large part to it publicly owned fast, affordable, reliable network. Years ago, the city of Lafayette, Louisiana, built the LUS Fiber network to connect homes and business.

Now, LUS Fiber is helping to diversify Acadiana’s economy, which once almost exclusively relied on the oil industry. Fiber networks offer much potential for economic development. 

“The State of Business” in the Silicon Bayou

The October-November issue of the Acadiana Profile at MyNewOrleans.com ran an article on the changing landscape of Acadiana’s businesses. Author Kimberly Singletary provides an overview of three growing industries: technology, manufacturing, and healthcare. All three need access to reliable, high-speed connections.

Singletary spoke with One Acadiana, an economic development organization in Lafayette:

“We’ve had a long history of innovation in IT and software,” says Jason El Koubi, CEO of One Acadiana. “But it's still very much an emerging field.”

Due to what El Koubi describes as “almost a grassroots movement in cultivating IT over the years,” the Acadiana region enjoys a robust offering of internet services resulting in a competitive, cheap and extremely fast LUS Fiber network.

LUS Fiber offers affordable, high-speed connectivity to several software developers that have made Acadiana their new home. The network offers speeds of up to 2 Gigabits (2,000 Megabits per second). In 2014, LUS Fiber attracted three companies, bringing almost 1,000 jobs to the “Silicon Bayou.” Another company, Waitr, an Uber-like food delivery service, is planning to add an operations center to Lafayette, which will bring another 100 jobs to the community.

More Than Tech: Industries Need Connectivity

Chanute's FTTH Project on Hold Indefinitely

Changes in leadership in Chanute have put the community's FTTH plan in suspended animation. In April, the City Commission decided to delay financing shortly before the scheduled bond sale. It is unfortunate that residents and businesses will lose the opportunities the fiber deployment would bring. Nevertheless, they deserve the right to make their own choices, good or bad.

The community of Chanute deployed a network incrementally with no borrowing or bonding in order to improve efficiencies, save public dollars, and control connectivity for municipal facilities. Local schools and colleges, struggling to compete, began taking advantage of technology in the classroom and expanded distance learning. The network eventually created a number of economic development opportunities when community leaders started providing better connectivity to local businesses. We told Chanute's story in our 2013 report "Chanute's Gig: One Rural Kansas Community's Tradition of Innovation Led to a Gigabit and Ubiquitous Wireless Coverage." 

Chanute made history when it was the first municipality in Kansas to obtain permission from the Kansas Corporation Commission to issue bonds for the project. They also became the first municipality in the state to seek and receive "eligible telecommunications carrier" (ETC) status. Chanute was awarded over $500,000 in Rural Broadband Experiment Funds from the FCC. Whether or not they will still be able to take advantage of those funds remains a question. After taking action and putting so many of the necessary pieces in place, it is disheartening to see the plan abandoned by politicians.

Regardless of the future of the FTTH project, Chanute has the infrastructure in place to encourage more economic development, connect community anchor institutions, and allow the community to control its own costs. The FTTH project is still a possibility.

Chanute and Chattanooga Added to List of Rural Broadband Experiment Funds

A year ago, the FCC accepted applications from entities seeking Connect America funds for rural broadband experiments. After provisional awards and some eliminations, Chanute's FTTH project, Chattanooga's EPB, and a number of additional cooperatives are now on the list of provisional winners reports Telecompetitor.

According to the article, $27 million became available when 16 entities were eliminated for various reasons.

A recent Chanute Tribune article reports that the city's expected award will be approximately $508,000 if it passes the FCC's post-selection process. Mikel Kline, a consultant working closely with the city on its FTTH project told the Tribune:

It is Kline’s understanding that this $508,467 would be cost support for the city’s Fiber to the Home network over the next six years. It requires the city to become an eligible telecommunications carrier, and to finance and construct the fiber network.

This money can be used to pay operational costs or offset a portion of the debt on the city’s investment in the local infrastructure over the next six years.

Remember that Chanute has developed its fiber infrastructure incrementally over more than two decades. The community is moving ahead with its FTTH project to share the benefits of fiber with residents and more businesses after bringing better connectivity to schools, municipal facilities, and a growing number of businesses. 

Recently, the city applied for and received state approval to bond for deployment costs. A 1947 state law required the application be filed with the Kansas Corporation Commission, the state entity concerned with utility regulations. According to Kline, the city has also applied for eligible telecommunications carrier (ETC) status. This designation will allow the city, as a common telecommunications carrier, to obtain Kansas Universal Services Funds.

Chanute Receives State OK to Bond for FTTH Deployment

The Kansas Corporation Commission (KCC) will allow the city of Chanute move forward with its plan to serve residents and local businesses with its municipal network reports the Wichita Eagle. KCC staff had recommended that the community, which has built out a network over the course of decades, receive KCC approval. 

In keeping with an antiquated 1947 state law, K.S.A. 10-123, the city needed KCC approval to issue the revenue bonds. In keeping with the statutory requirements, the KCC found that the expansion is necessary and appropriate for the city, its consumers and investors. The KCC also also determined that the expansion will not duplicate an existing utility service.

In its filing [PDF], Chanute indicated that its network is an essential part of the local economy and the community's future:

Chanute is a rural community, and like all rural communities, access to broadband is fundamental to the well-being of its citizens and even to the survival of the community itself. Chanute does not need to convince the Commission of the importance of having access to a high- speed broadband network. The Commission is well aware of that need. The investments contemplated for Chanute's broadband network are necessary and appropriate to allow Chanute to meet that need in its territory.

As the city points out, incumbents AT&T and Cable One, do not offer anything close to the level of service of the planned gigabit FTTH network. As we cover in our 2012 report on Chanute, AT&T and Cable One seem to have no interest in serving the community beyond minimum expectations. It was the need for better services that inspired the city to build out its infrastructure and offer services to local businesses.

Community Broadband Media Roundup - December 12, 2014

This week in Community Broadband networks... partnerships, cooperatives, and going-it-alone. For a background in muni networks, check out this recent article from FiscalNote. The article highlights Kansas and Utah's fight for improving beyond the minimum speeds. 

Speaking of minimum, the FCC announced its new "rock bottom" for regulated broadband speeds. Ars Technica's Jon Brodkin reports that despite AT&T, Verizon, and the National Cable and Telecom Association's protests, ISPs that use government subsidies to build rural broadband networks must provide speeds of at least 10 Mbps for downloads.

Rural Americans should not be left behind those who live in big cities, the FCC announcement today said. "According to recent data, 99 percent of Americans living in urban areas have access to fixed broadband speeds of 10/1, which can accommodate more modern applications and uses. Moreover, the vast majority of urban households are able to subscribe to even faster service," the FCC said.

The FCC plans to offer nearly $1.8 billion a year to carriers willing to expand service to 5 million rural Americans. 

This is a step in the right direction, but we are alarmed to see a download:upload ratio of 10:1. People in rural areas need to upload as well as download - our comments to the FCC strongly recommended raising the upstream threshold as well and we are very disappointed to see that remain a pathetic 1 Mbps.

And, from TechDirt's own "who can you trust if you can't trust the phone company department," Karl Bode found that a study by the AT&T-funded Progressive Policy Institute concluded that if Title II regulations were passed, the nation would be "awash in $15 billion in various new Federal and State taxes and fees. Bode writes that the study cherry-picked and conflated data:

Chanute City Leaders Approve Financing Strategy for FTTH in Rural Kansas

Chanute's City Commission passed a motion this month to fund its planned FTTH project with revenue bonds, bringing the entire community closer to fast, affordable, reliable connectivity, reports the Chanute Tribune

In addition to authorizing a plan to secure $18.9 million in revenue bonds, the motion also included funds for a pre-deployment baseline analysis focused on economic development and funds to hire an attorney. The bonds include debt service reserve funds and additional funding to make early interest payments. The plan determines the city will pay off the investment in a little over 14 years, based on a 45 percent take rate.

The Kansas Corporation Commission (KCC) must approve the plan. The KCC is a state regulatory body with a variety of responsibilities, including regulating telecommunications utility rates. The KCC also handles rates for electricity, natural gas, and liquid pipeline services. They handle safety issues, licensing, energy conservation, etc. If the KCC does approve the plan, the bonds can be secured without a public vote unless the city receives any petitions. Chanute still plans on providing residential gig service for $40 per month.

According to the Tribune, 62 percent of 1,030 returned surveys indicated yes or maybe as to whether or not they would be interested in signing up for high-speed service at home or at work; 38 percent said no. City officials are optimistic that the project will blossom even beyond those figures:

“I think once it starts rolling out, a lot of people will see what type of services they’re getting through the city,” [Mayor Greg] Woodyard said, “and they’ll get those bundle packages and we’ll be able to offer them a better product than they’re currently getting at a cheaper price. I think more people will sign up for it in that point in time.”

Woodyard also noted that Chanute is setting an example for other Kansans suffering from poor connectivity:

“A lot of other communities are looking at starting to do this, possibly,” Woodyard said. “We are the trendsetters for the state of Kansas. Everybody’s looking at us to see how we go through the process of doing the fiber project.”