WhipCity Fiber Charges Forward in Westfield and Massachusetts Despite Pandemic

Westfield Gas+Electric (WG+E) started its broadband division WhipCity Fiber and the buildout of their network five years ago. The project started with only serving Westfield, but WG+E is now contracting with other small towns in Massachusetts to assist in building and potentially operating their own fiber networks.

Today, WG+E is slated to help connect 12,400 households in 20 Massachusetts towns over the next 10 years. In order to do this, WG+E and WhipCity Fiber will receive more than $10 million over the next ten years through the Federal Communication Commission’s Connect America Fund Phase II auction, which awarded $1.5 billion in subsidies to broadband providers to expand rural connectivity across the nation. The 20 towns that are partnering with WG+E to build fiber networks are: Alford, Ashfield, Blandford, Becket, Charlemont, Chesterfield, Colrain, Cummington, Goshen, Heath, Leyden, New Ashford, New Salem, Otis, Plainfield, Rowe, Shutesbury, Washington, Wendell, and Windsor.

Adapting While Expanding

Westfield has been slowly building out its network, which is owned and operated by WG+E, and it is now roughly 75 percent complete. Lisa Stowe, the communications manager at WG+E, said that they temporarily paused new installations in Westfield due to the Covid-19 pandemic. However, she is hopeful that they will begin connecting new customers and resume their buildout of the network this year.

Image

To construct the WhipCity Fiber network, Westfield issued a $15 million bond. The city must pay down that bond and do routine updates to the network as they continue expanding. Stowe explained that they are well on track to having the network fully constructed within their original six year timeline.

More FTTH Projects In Massachusetts Hilltowns

Two more western Massachusetts towns are ready to move forward with their municipal networks. Ashfield and Shutesbury both plan on working with Westfield Gas+Electric (WG+E) to bring Fiber-to-the-Home (FTTH) to their communities.

Funding Release Allows Projects To Move

Earlier this year, state officials at the Massachusetts Broadband Institute (MBI) decided to release state funds to local communities so they could finally begin their last-mile projects. Ashfield, population approximately 1,750, received $1.4 million and Shutesbury, population about 1,800, received $870,000; each town’s award should cover about one-third of the cost to deploy their planned municipal FTTH networks.

Shutesbury hopes to connect every premise for an estimate of $2.5 million and expects the project to be complete by 2019. Ashfield also intends to include every property; its Municipal Light Plant (MLP) will operate the infrastructure and partner with a private form for network operations and ISPs for service to the community. WG+E will provide support to Ashfield for design, engineering, and construction. Shutesbury plans to work with WG+E during planning and construction.

Westfield Showing The Way

The two communities join nearby Otis, a town of 1,687 premises, which also hired WG+E to help them deploy their fiber optic network. In June, WG+E trucks started to roll into Otis and begin work on the new project. Towns in western Massachusetts that qualify for the funding have looked to Westfield for guidance ever since the community deployed its WhipCity FTTH network. Westfield has expanded within its own borders and is now embracing its role as a mentor and agent.

Fiber Optic Otis: FTTH Service To Start This Fall

People in Otis, Massachusetts, are now seeing utility crews make space for fiber optic cable on poles as they prepare for the community’s publicly owned Internet network. The schedule calls for cable installation in August; the network should start serving residents and businesses this fall.

Working With A Neighbor

Like several other hill towns in western Massachusetts, Otis is working with Westfield Gas + Electric’s WhipCity Fiber, which will handle construction of the network. WhipCity will construct the network in phases, connecting premises as neighborhoods are completed. The project will connect 1,687 premises and will cost approximately $5 million. 

Construction is finally able to commence because in May, the Massachusetts Broadband Institute (MBI) released funding for last mile broadband networks to several towns that advocated for their own solutions. Otis received $1.7 million. Communities like Otis that chose to invest in publicly owned infrastructure are required to contribute to the cost of their network.

MBI chose to release the funds after a drawn out situation in which unserved and underserved communities in the western part of the state first planned to unite as a broadband cooperative, WiredWest. MBI was the administrator of approximately $50 million in federal stimulus and state grant funding but withheld the funds. They felt there were problems with the WiredWest business model, but local towns and municipal network experts did not share those concerns. Instead, MBI planned to dole out the funding to large incumbent providers, which angered many of the local communities that have expressed dissatisfaction with treatment by those very companies over the years. Comcast will still obtain large amounts of the grant money to build out in several of the smaller communities. Those small towns will not be required to contribute, but 100 precent of their premises are not always served and they will not own the infrastructure.